Basic information about the window project for BRF Platån

We will here collect and translate the most important information about the project.

The preliminary schedule for the project is:

We will work through all buildings in the following order:

Flintlåsv. 1 Jun – Jul -20
Lodv. 2 Jul – Aug -20
Lodv. 4 Aug – Sep -20
Lodv. 6-8 Sep – Okt -20
Lodv. 10-12 Okt – Nov -20
Lodv. 14 Nov – Dec -20
Lodv. 16-18 Jan -21
Flintlåsv. 39-45 Feb -21
Flintlåsv. 29-37 Feb – Mars -21
Flintlåsv. 19-27 Mar -21
Flintlåsv. 9-17 Apr -21
Flintlåsv. 38-44 Apr – Jun -21
Flintlåsv. 26-34 Jun – Jul -21
Flintlåsv. 2-18 Aug – Okt -21

More information will be distributed closer to the actual date for your apartment.

What is the project about?

Our windows are almost 60 years old and are in a bad shape.
So the förening has desided to install new windows in alla apartment and in the basement.
The only window that will not be replaced is the window at the balcony.

More information will follow. Please check back here once in a while.

More information will be distributed closer to the actual date for your apartment.